Free working document
The weather day log and notice template
A one page fill in record for the morning it rains, built so a reviewer who was never on your site can follow the day from the first gauge reading to the notice that went out.
This is the working document behind RainDelayLog, written out so you can use it on paper or in a spreadsheet before you use it in the app. It follows the order a weather day is actually challenged: was there measurable weather at an acceptable source, did it stop controlling work, what did it cost in hours, and did written notice go out on time. Fill it in the same morning and the day defends itself. Fill it in from memory in October for a day in April and it will not.
The template is written for a US commercial site running under a standard owner agreement, so it assumes a named or nearest qualifying station, a threshold in the clause, a notice window measured in calendar days, and a monthly anticipated weather day allowance. Adjust the threshold and the window to match your contract before you print it, because those two values are the ones a reviewer checks first.
Set up before the season, once per job
The morning it hits, before the crew is released
Before you leave the gate that day
Inside the notice window
How to use it
Use it in the order it is printed. The most common failure we see is a superintendent who fills in the narrative and the photos beautifully and never touches the notice section, which means a well documented day gets struck on a procedural point that had nothing to do with the rain. The last group is the one that saves the day, so run it even when the site is chaotic.
Two habits make the rest work. First, one entry per event on the same morning, never a weekly catch up, because reviewers can tell the difference and so can you at month end. Second, keep the days you worked through in the record as well. A log that only appears when it rains looks written for a claim, while a continuous record with normal days in it is the thing that makes your rain days credible.
Send me the editable copy
Send it to your inbox as an editable file you can adapt to your own weather clause, threshold and notice route before the next storm.
Questions about this document
Can I use this on paper in the trailer?
Yes, it is designed to print on one sheet front and back. Plenty of superintendents run the paper version at the gate and hand it to the project engineer to enter later that morning. Just make sure the photos and the station reading get attached the same day.
How is this different from our daily report?
A daily report describes the working day for the project team. This describes a weather event for a reviewer who was never there and who is looking for a reason to strike the day. The evidence, the order and the notice tracking are all different.
What if my contract has no weather clause at all?
That is worth raising with your counsel before the next job. Without a clause you are usually arguing under general delay and force majeure provisions, and the evidence burden goes up rather than down. The template still applies; the threshold line is just yours to define.
Filling it in is the work, remembering it is the problem
Once the clause, the station distance and the anticipated day table are written on the front page, the template does its job and the discipline becomes daily. Somebody has to reach for it at 6:30 with the crew arriving, count the released hours before anyone drives off, flag tomorrow as a dry out day and watch the notice due date. A demo shows that same sequence prompting itself and the packet assembling in claim order as you go, so the record does not depend on who is standing on the site that week.